Track Renewal Works Between Bilecik and Karaköy (Yayla) Stations

Client: Turkish State Railways (TCDD) 1st Regional Directorate, Istanbul
Scope of Works:
Turkish State Railways (TCDD) 1st Regional Directorate, Istanbul – 6.5 km of Existing Railway Line:
- Dismantling of Track Laying Machine Belonging to the Authority
- Loading onto Wagons, Unloading, and Distribution within Depot Area
- Preparation of Infrastructure
- Preparation of Panel Production Area for Manufacturing 36 m Frames with UIC 60 Rails and B70 Sleepers
- Unloading of 36 m UIC 60 Rails and B70 Sleepers from Wagons
- Loading of Prepared Panels onto Wagons and Laying with Track Laying Machine
- Loading of First Layer Ballast onto FB Wagons and Unloading onto Track
- Dismantling of 4 Existing Turnouts
- Installation of 4 R300 Turnouts
- Installation of 1 R500 Turnout (From Conventional Line to High-Speed Rail Line)
Construction Period: September 2013 – December 2013