Azman Stream Flood Protection and 3 Bridge Works (Lot 2), Yıldırım Beyazıt University Çubuk Campus

The Lot 2 contract for the section of Azman Stream running through Yıldırım Beyazıt University's Çubuk Campus was carried out with the DSİ General Directorate's Flood Control Department. A 2,000 m trapezoidal concrete channel, 110 m of reinforced concrete U-channel with transition structures, and three road bridges were built. An irrigation pond and a reinforced concrete outlet structure were also within the scope. The project was completed between January 2024 and August 2025.

Scope of work

  • 012,000 m trapezoidal concrete channel
  • 023 road bridges
  • 03110 m U-shaped concrete channel and transition structures
  • 04Irrigation pond and outlet structure

Site photos

Azman Stream Flood Protection and 3 Bridge Works (Lot 2), Yıldırım Beyazıt University Çubuk Campus – Photo 1

1 / 5

Planning a similar project?

Give us 15 minutes with your project team and we will walk you through our capacity and references.

Request a quote