Beykoz Riva Bridge and Approach Roads

For the Istanbul Metropolitan Municipality, a 155 m prestressed precast beam bridge was built over the Riva River, together with roughly 800 m of junction arms on both approaches. Stability was achieved with Ø165 cm bored piles reaching 65 m deep under the bridge foundations, and with stone columns of sufficient length and number along the approach roads. The existing 120 m steel bridge that carried traffic across the river was dismantled and removed with divers and other marine equipment. All electricity, lighting, telecom and water infrastructure in the project area was also renewed as part of our scope.

Scope of work

  • 01155 m prestressed precast beam bridge over the Riva River
  • 02Junction arms and approach roads on both sides (~800 m)
  • 03Ø165 cm bored piles, 65 m deep
  • 04Stone column works
  • 05Electricity, lighting, telecom and water supply infrastructure
  • 06Retaining structures
  • 07Dismantling of the existing 120 m river bridge using marine equipment

Site photos

Beykoz Riva Bridge and Approach Roads – Photo 1

1 / 3

Planning a similar project?

Give us 15 minutes with your project team and we will walk you through our capacity and references.

Request a quote